Building Progress of PERKOBP Centre

After 17 years of persistence on the cause of improving the quality of life of persons with learning difficulties through vocational training and employment, members of PERKOBP finally see that their dream is coming true. A centre for persons with learning difficulties. The new centre would provide a better working environment; allow those on the long waiting list to have a chance of being trained; provide respite care to parents via a Day Care Centre; introduce more vocational skills, etc.

The construction of the centre is undertaken by Universal Construction Management with a cost of RM800,000.00 and a contingency provision of RM80,000.00. Completion date is now expected to be by end of 2012.

Donor List…

Clearing of land.

Clearing of land started in early November 2010. The land had grown many matured fruit tress like rambutan, mango, Jack fruit, papaya and banana. However, all of them had to give way to the building. The workers said they also found many snakes and tortoises on the land! The following pictures shows the land before and after it had been cleared.

Piling Work.

Piling work started 22nd November 2010 and completed in a week’s time.

Making the Drains.

In December 2010, two teams were employed to construct the drains on the right and left side. The drains connect to the monsoon drain in front and would channel away the rain water. (bottom left picture)

Work on the pile spots started just around the 20th December where an excavator was used to dig up the earth surrounding the concrete piles in order to prepare for footing work. Subsequently, a worker was deployed to trim down the piles of all the 25 pile spots.

Making the Pile-caps.

Following pictures show the completion of making the pile-caps…

Making the Ground Beams

By 9th January 2011, the ground beams were all installed.

Making Ground Floor Slab and Pillars.
Erecting Truss to Make 1st Floor Form-work.
Making 1st Slab & Beams.
Making 1st Slab & Form-work for Pillars.
Pillars and Roof Beams Completed.
Constructing the Ground Floor Walls.
Constructing the Entrance Wall.
Construction Site cordoned off by MPSJ
Briefing held on 17th May 2011 at Dewan JKK, Kg. Tengah B
×

 